Iron ore fixed plant shutdown
- Client type
- Operator
- Challenge
- 14-day fixed plant shutdown with a fixed restart date and a large emergent work risk.
- Approach
- Built a fully resource-loaded Primavera P6 schedule from the work packs, with daily progress updates and critical path tracking through execution.
- Result
- Full scope delivered two days ahead of plan.